Program Progress
38%
- Planned / rig
- 28.0 m/day
- 14-day avg / rig
- 0.0 m/day
- Overall avg / rig
- 34.3 m/day
- Days to project target
- — No recorded production in the last 14 days
Rig operability
| Prospect | Remaining metres | 1 rig / 2 shifts | 2 rigs / 2 shifts | 3 rigs / 2 shifts |
|---|---|---|---|---|
| North Ridge | 590.0 m | 17.2 days | 8.6 days | 5.7 days |
| Silver Creek | 1335.0 m | 38.9 days | 19.4 days | 13.0 days |
| West Fork | 1860.0 m | 54.2 days | 27.1 days | 18.1 days |