Rig 12 Active Track-mounted diamond drill assigned to the program. ContractorNorthern Diamond Drilling TypeDiamond Holes3 Average37.1 m/day Current1704.5 m Current holeNR-26-105 Completed Holes NR-26-102May 19, 2026 NR-26-101May 12, 2026 Upcoming No upcoming holes assigned. Drilling Time Curves 1705 m / 46 days = 37.1 m/day NR-26-101 NR-26-102 NR-26-105
Rig 18 Active Track-mounted diamond drill assigned to the program. ContractorSummit Drilling TypeDiamond Holes2 Average30.5 m/day Current1007.3 m Current holeSC-26-104 Completed Holes SC-26-103May 25, 2026 Upcoming No upcoming holes assigned. Drilling Time Curves 1007 m / 33 days = 30.5 m/day SC-26-103 SC-26-104
Rig 24 Standby Track-mounted diamond drill assigned to the program. ContractorValley Core Services TypeDiamond Holes0 Average28.0 m/day Current0.0 m Next hole- Completed Holes No completed holes yet. Upcoming No upcoming holes assigned. Drilling Time Curves 0 m / 0 days No depth curves yet.