Drillhole
3:16 PM Jun 5, 2026

North Ridge

NR-26-101

Completed

Rig Rig 12

Hole Properties

Drill order
Completed
Pad
NR-01
Rig
Rig 12
Prospect
North Ridge
Core size
NQ
Azimuth / dip
47.0 / -58.0
Coordinates
486030.00 E 7084992.00 N
Start date
April 17, 2026
Last update
Jun 1, 5:04 AM
End date
May 12, 2026 25.2 days drilled
Final depth 628.4 m
Planned depth
Next target ETA
EOH ETA
Rate model 37.1 m/day rig history by active day: 1704.5 m / 46 active rig-days
Directional plan 0.0 days

Add Update

You can view updates, but cannot add them.

Update History

  1. Depth update demo_maintainer Depth 628.4 +103.4 m Status Completed

    Depth and status update from the drill crew.

  2. Depth update demo_maintainer Depth 525.0 +39.2 m Status Drilling

    Depth and status update from the drill crew.

  3. Depth update demo_maintainer Depth 485.7 +32.0 m Status Drilling

    Depth and status update from the drill crew.

  4. Depth update demo_maintainer Depth 453.7 +27.8 m Status Drilling

    Depth and status update from the drill crew.

  5. Depth update demo_maintainer Depth 425.8 +25.0 m Status Drilling

    Depth and status update from the drill crew.

  6. Depth update demo_maintainer Depth 400.8 +24.0 m Status Drilling

    Depth and status update from the drill crew.

  7. Depth update demo_maintainer Depth 376.8 +18.5 m Status Drilling

    Depth and status update from the drill crew.

  8. Depth update demo_maintainer Depth 358.3 +19.9 m Status Drilling

    Depth and status update from the drill crew.

  9. Depth update demo_maintainer Depth 338.4 +19.8 m Status Drilling

    Depth and status update from the drill crew.

  10. Depth update demo_maintainer Depth 318.6 +23.2 m Status Drilling

    Depth and status update from the drill crew.

  11. Depth update demo_maintainer Depth 295.4 +17.5 m Status Drilling

    Depth and status update from the drill crew.

  12. Depth update demo_maintainer Depth 277.8 +16.0 m Status Drilling

    Depth and status update from the drill crew.

  13. Depth update demo_maintainer Depth 261.8 +28.5 m Status Drilling

    Depth and status update from the drill crew.

  14. Depth update demo_maintainer Depth 233.3 +21.8 m Status Drilling

    Depth and status update from the drill crew.

  15. Depth update demo_maintainer Depth 211.6 +15.9 m Status Drilling

    Reduced advance during bit change and ground conditioning.

  16. Depth update demo_maintainer Depth 195.7 +15.4 m Status Drilling

    Depth and status update from the drill crew.

  17. Depth update demo_maintainer Depth 180.3 +24.0 m Status Drilling

    Depth and status update from the drill crew.

  18. Depth update demo_maintainer Depth 156.3 +18.5 m Status Drilling

    Depth and status update from the drill crew.

  19. Depth update demo_maintainer Depth 137.8 +14.5 m Status Drilling

    No drilling on day shift while waiting on helper coverage.

  20. Depth update demo_maintainer Depth 123.3 +19.8 m Status Drilling

    Depth and status update from the drill crew.

  21. Depth update demo_maintainer Depth 103.6 +23.2 m Status Drilling

    Depth and status update from the drill crew.

  22. Depth update demo_maintainer Depth 80.3 +14.0 m Status Drilling

    Depth and status update from the drill crew.

  23. Depth update demo_maintainer Depth 66.3 +16.0 m Status Drilling

    Short shift while water line repairs were completed.

  24. Depth update demo_maintainer Depth 50.3 +28.5 m Status Drilling

    Depth and status update from the drill crew.

  25. Depth update demo_maintainer Depth 21.8 +21.8 m Status Drilling

    Depth and status update from the drill crew.

  26. Status update demo_maintainer Status Drilling

    Hole started. Casing set and drilling underway.