Program Progress
Forecast37%
- Current
- 2712 m
- Planned
- 7270 m
- Remaining
- 4558 m
- Expected completion
- 67.5 days Aug. 12, 2026 at 67.6 m/day from 2 active rigs
Rig operability
| Prospect | Remaining metres | 1 rig / 2 shifts | 2 rigs / 2 shifts | 3 rigs / 2 shifts |
|---|---|---|---|---|
| North Ridge | 590.0 m | 17.2 days | 8.6 days | 5.7 days |
| Silver Creek | 1335.0 m | 38.9 days | 19.4 days | 13.0 days |
| West Fork | 1860.0 m | 54.2 days | 27.1 days | 18.1 days |