Total planned
7,200 m
2026 project target
To date
2,712 m
38% of annual target
This month
2,712 m
from depth updates
Pads ready
4
6 total pads
Drillholes
3 / 8
completed of planned
Drill Collar Map
Currently Drilling
| Hole ID | Status | Depth | Next target | EOH ETA | Prospect | Pad | Rig |
|---|---|---|---|---|---|---|---|
| NR-26-105 | Drilling 14.0 days | 384 m / 820 m |
Upper vein 455 m, June 1, 2026 |
June 11, 2026 | North Ridge | NR-02 | Rig 12 |
| SC-26-104 | Drilling 17.0 days | 436 m / 780 m |
Main vein 585 m, June 4, 2026 |
June 11, 2026 | Silver Creek | SC-01 | Rig 18 |
Recently Completed
| Hole ID | Status | Depth | Start date | End date | Duration | Prospect | Rig |
|---|---|---|---|---|---|---|---|
| SC-26-103 | Completed | 571 m / 565 m | April 28, 2026 | May 23, 2026 | 25.8 days | Silver Creek | Rig 18 |
| NR-26-102 | Completed | 692 m / 700 m | April 22, 2026 | May 17, 2026 | 25.8 days | North Ridge | Rig 12 |
| NR-26-101 | Completed | 628 m / 620 m | April 15, 2026 | May 10, 2026 | 25.8 days | North Ridge | Rig 12 |